According to the news report I saw, the knob floated in between the window pane and the back of an instrument panel while the interior of the spacecraft was "inflated" to 14.7 psia on orbit. I wonder if they have considered pressurizing the vehicle to 29.4 psia, which would give the same delta-p (29.4 - 14.7 atmospheric = 14.7 delta-p) across the structure that is present on orbit, when there is no effective atmospheric pressure on the outside of the vehicle? At least they might be able to get the knob out of the way. Of course, I am not familiar enough with the orbiter's systems to know if the overpressurizing is practicable or not.
And that still doesn't determine if the pane is damaged! 🙁 Always something!
Ad LEO! Ad Luna! Ad Ares! Ad Astra!
Looks like a job for a hacksaw blade 😉
Any self respecting thug from the bad side of town should be able to get that window out PDQ. Just set an Ipod on the seat and the knob issue will go away over night.
As per the article now on sdc. Atlantis is scheduled to fly just twice more. So, there will not be any long delays. If the problem does not get fixed, then the other orbiters will fly.
As noted they will be pressurizing to 18 pounds per square inch. That will be an interesting test.
The most concerning statement to me is this. "Small gouges already have been detected." Given the tolerances quoted above, you wonder when they are going to be saying that they need to replace the window, if they want to fly this orbiter.
I hope that is not the case. This is a weird one. You can't plan for most weird ones. Oh well.
From what I've read this seems so stupid ! Your NASA you have so many engineers and maintenance people working for you and you don't know if you can repair a window ! It makes sense why people don't want NASA to have money I mean why can't you fix a window in Florida instead of sending it to California (I do understand the factory/company no longer exists but still) !
yes if not correct it could risk the crews safety, but still not knowing if you can fix a window and if not to retire a billion dollar space craft. It is really stupid to send a whole vehicle to the other coast to have a window repair things like that should be able to done right at the space center in Florida.
seth, what gave you the idea they would send the whole vehicle to the other coast? I haven't seen that anywhere.
This is not just a window, it is part of the pressure hull for the orbiter, so they need to be very careful. If any scratches are more then cosmetic, it could lead to the window cracking during flight, possibly leading to loss of the crew. That would be bad. It's not like a crack in your windshield.
If the damage would create such a risk, it would have to be replaced. Since the manufacturing facilities no longer exist for the windows, it would take months or years to fabricate a new one, and the Shuttles won't be flying by then. So the most efficient thing to do might be to just shift those 2 missions to the other orbiters. That would allow the remaining shuttle flights to be completed.
Get a clue 🙂
Wayne
then I inferred a little too much I figured since the article that I read said the last time they had been replaced was during overhauls so I figured they had just sent the whole orbiter. But still why wouldn't they have spares but if repairing it would take so long I guess I see why to just end it now instead of waste the money.
I was trying to say if it couldn't be fixed they should mothball it early like said but I don't like the word/words mothballing
Rumor (mentioned at today's STS-127 CSB) is that the window has passed the test and there will be no delay due to it.
That's not the reason for the delay if the window needed to be replaced from what I recall. It was the racks of equipment in front of it that would have to be remeoved to allow access; then reassembled, then retested, etc. It's not like replacing a windshield on yer car 🙂
lol, I know that. But still. The shuttle compartment isn't that big. From the NASA videos I've watched, there doesn't seem to be a lot of equipment, just that it's bolted into the rack. It doesn't take months to unbolt equipment, move it, test it, and put it back in and do another test. Military does bigger setup's and tear downs daily. All they really need is the right people with an organized schedule. The problem I think is getting the right people off their butt to complete the job in a timely manor. I understand there isn't much maneuverability inside the shuttle, but still. If they really wanted to get the work done in a timely manor, trust me... it could be done.