Re: STS-131 Pre Launch Discussion
There is some error with video in your last post. I found this to be working :
[youtube]http://www.youtube.com/watch?v=owLGXHOWS8A[/youtube]
Re: STS-131 Pre Launch Discussion
I tried it now, and it's just like you said .. Thanks for explaining 🙂
Re: STS-131 Pre Launch Discussion (Target April 5)
NASA let us contractors bring non badged people onto KSC for the roll out of the VAB early this nornning ( 2358 hrs local). We were there for about 1 1/2 hours. At the vehicle's closest approach we were about 100 meters away.
My wife had never seen a rollout. She was impressed!!
Back on the Apollo program we were allowed to bring loads of people in for every rollout. The difference is the Shuttle has the SRBs which, ofcourse, are fully loaded with propellant and the Shuttle Orbiter has residual hypergolic prop. from it's previous mission.
Re: STS-131 Pre Launch Discussion (Target April 5)
Is this an unusually short time between roll out and TCDT, which is still scheduled for Friday? I would have thought the time required to connect up and tie down the stack would mean they would be doing the TCDT next week...
Re: STS-131 Pre Launch Discussion (Target April 5)
Rollout Timelapse:
[youtube]http://www.youtube.com/watch?v=0SKsHPw_0_A[/youtube]
NasaTV Rollout Recap:
[youtube]http://www.youtube.com/watch?v=P057NtvR3i0[/youtube]
Re: STS-131 Pre Launch Discussion (Target April 5)
shuttle_guy: I have to say I am so envious of you.
Working on the program and being able to watch the roll outs, and launches.
I'd die for a job at the Cape.
Re: STS-131 Pre Launch Discussion (Target April 5)
[youtube]http://www.youtube.com/watch?v=GPvxOWOSZCE[/youtube]
Re: STS-131 Pre Launch Discussion (Target April 5)
This spacewalk looks very tricky, from the timing point of view. The ammonium leak has caused some concern during the STS-130, but it seams they think it has much lower chances for leaking this time.
They are all over the structure, and i find it very impressive, even though they say 'it's not a complex spacewalk'..
Re: STS-131 Pre Launch Discussion (Target April 5)
[youtube]http://www.youtube.com/watch?v=6L61bY7ZZas[/youtube]
First two minutes are STS-131 related:
[youtube]http://www.youtube.com/watch?v=kHaj6EbxIuI[/youtube]
Re: STS-131 Pre Launch Discussion (Target April 5)
We have a problem in the right OMS pod. One or both of the RCS helium isolation are leaking very badly. We would have to roll off the pad and take the Orbiter off the ET to repair this item. However I think we will fly the problem as is since there are 2 more levels of of protection.
A roll back would delay the launch by weeks.
Re: STS-131 Pre Launch Discussion (Target April 5)
Today's NASA Release:
Testing of Discovery's Systems Continue
Wed, 17 Mar 2010 08:47:00 AM EDT
On Launch Pad 39A at NASA's Kennedy Space Center in Florida, technicians completed a test to pressurize space shuttle Discovery's Right Reaction Control System's helium tank to verify the overall health of the regulators downstream of the helium isolation valves. Preliminary data shows positive results for the test. Today, crews will begin preparing Discovery for further testing on the system.
The testing was initiated because of an issue that occurred over the weekend while Discovery's aft fuel propellant tanks were being vented in preparation for fuel loading. The Right Reaction Control System, or RRCS, fuel helium tank pressure unexpectedly decreased in unison with the RRCS fuel propellant tank when the fuel tank was vented. This indicates that at least one of the two parallel helium isolation valves is leaking or is remaining in the open position when it is expected to be closed.
The two helium system regulators, a primary and a secondary, will be tested to verify they are functioning correctly. The regulators are "downstream" of the isolation valves, and help to maintain helium pressure to the fuel tank. Knowing whether the regulators are operating correctly is a key factor for managers who must decide whether to launch with the errant condition of the isolation valves. The test is expected to occur late this week once a ground support equipment test panel has been calibrated. The helium system will be brought to flight pressure and engineers monitoring the panel will ascertain whether the regulators function properly.
Also this week, managers are targeting Friday to move Discovery's payload to Launch Pad 39A, starting at 12:01 a.m. EDT.
There still are a few days of contingency left in the schedule to make the targeted launch date of April 5.
Re: STS-131 Pre Launch Discussion (Target April 5)
[youtube]http://www.youtube.com/watch?v=x5DJZyXQvT4[/youtube]