So that spent $450 million and only needed $85M to finish the project. Then, to save money they toss the $450M in the trash.
They waste $450M to save $85M. ONLY the government would even concider such a stupid plan.
Perhaps NASA ought to be considering the ASTROLAB rover with respect to its ability to perform on that contract. It’s still dependent on private sector funding.
The article says that the "launch costs" for the VIPER were not included in the $85M "saved" by cancelling the project.
It would be helpful to know what the additional costs were besides those covered by the $85M.
They're scraping up money to spend on other priorities. We ought to defund other projects, maybe artistic ones instead of scientific ones. We all have to prioritize and economize.
From that "other website", here is the answer to my question about what other costs were saved or potentially saved:
"The rover is now complete, but is only now starting environmental testing. Kearns said the revised cost and schedule assumed that VIPER would get through that environmental testing without any problems. “I will you tell you that in general, spacecraft development system-level environmental testing does uncover problems that do need to be corrected, which would take more time and money.”
"Canceling VIPER now will save NASA a minimum of $84 million. That could grow, he said, if VIPER’s launch were to slip beyond November 2025, which would require waiting 9 to 12 months until the right lighting conditions return at the landing site in the polar region."
A lot of the cost overruns were attributed to delays in getting components due to the COVID pandemic disruptions.